SHOW OVERVIEW
RETURN TO CASE STUDIES

Kellogg DC

Haydock

Client: The Kellogg Company
Programme: 17 Weeks

Glencar undertook the fit out of a 525,000 sq ft warehouse occupied by Kellogg Company. Works were carried out while the facility was live and included the installation of racking, duct work, sprinklers and lighting to the main distribution facility as well as the creation of office space.

The 91-acre site, developed by Bericote Properties Ltd with funding from US investor Hillwood, is the company’s biggest distribution facility in the UK.

Calendar

17
Weeks

Size Icon

525,000
SQ FT

Client/End User: The Kellogg Company
PM/Client: Bericote Properties
Architect/Designer: UMC
Engineer: Hydrock
Programme: 17 Weeks

“I wanted to personally thank you for the effort in getting this project completed on schedule and being flexible working with us to support our distribution transition efforts. In normal times, this would have been a great accomplishment; during these unprecedented times, truly extraordinary. Please pass on our gratitude to other members of your team.”

Roger Nesti, Kellogg Company